Site Access Controls and Maintenance U.S. Department of Energy

Staff are on site 7 days per week performing security and maintenance activities. Tailings excavation and conditioning operations run 4 days a week.

In addition to excavating and conditioning mill tailings, the Project has excavated and sorted a portion of the mill building debris that was buried in the southern end of the tailings pile. Some debris is being shipped in containers modified to carry this type of material.

The Moab Project ships two trains a week, each carrying 136 containers. During the month of March, about 40,700 tons of tailings were shipped to Crescent Junction for disposal, for a total to date of about about 8,591,300 tons shipped.

Animated Line