Site Access Controls and Maintenance U.S. Department of Energy

Staff are on site 7 days per week performing security and maintenance activities. Tailings excavation and conditioning operations run 4 days a week.

In addition to excavating and conditioning mill tailings, the Project has excavated and sorted a portion of the mill building debris that was buried in the southern end of the tailings pile. Some debris is being shipped in containers modified to carry this type of material.

The Moab Project ships one train a day, 2 days a week, with up to 136 containers per train. During the month of February, about 36,400 tons of tailings were shipped to Crescent Junction for disposal, for a total to date of about about 8,550,700 tons shipped.

Animated Line